Concerning explosion and fire in the vicinity of vacuum gas oil desulfurization unit in Chiba oil refinery
(Third report, at 5:00 p.m.)

April 16, 2006
Cosmo Oil Co., Ltd.
Public Relations Office

At about 5:40 a.m. on April 16, 2006, an explosion and fire occurred in the vicinity of vacuum gas oil desulfurization unit in Chiba oil refinery (location: 2 Goikaigan Ichihara, Chiba, Executive chief: Takashi Yajima) of Cosmo Oil Co., Ltd. (Head office: 1-1-1, Shibaura, Minato-ku, Tokyo, Capital: 62.4 billion yen, President: Yaichi Kimura).
We would like to offer our sincere apologies for all the trouble and distress this incident has caused.
The circumstances at 5:00 p.m. are as follows.

Details
Date of occurrence April 16, 2006 (Sunday) at about 5:40 a.m.
Name of the facility Vacuum gas oil desulfurization unit (hereinafter HDS)/Hydrogen production unit No.1 (hereinafter HP)
Casualties None
Danger of secondary disaster None
Circumstances Around 5:10 a.m.: no abnormality found in patrol by an operator
Around 5:40 a.m.: explosion and fire occurred in the vicinity of HDS/HP
Around 5:42 a.m.: enquiry via Ichihara City Fire Department hotline; confirmed that Disaster Control Center had heard an explosion on the site
5:44 a.m.: reported the fire
Around 5:48 a.m.: announcement issued to defense services
8:19 a.m.: confirmation that the fire had been suppressed
8:44 a.m.: confirmation that the fire had been extinguished
9:35 a.m.: public fire department leaves site
Damage Damaged areas are being examined sequentially and by 5:00 p.m. the following three openings had been confirmed.
(1) Damage to overhead receiver of carbon dioxide absorption tower, hydrogen production unit No. 1
(2) Damage to water pipeline on framework (HP purified water pipeline, pipe size: 2 inches)
(3) Opening in flange area of oil pipeline under framework (oil pipeline of HDS product, pipe size: 6 inches)
Other damage
Some windows and roof slates in the facility and neighboring facilities were damaged.
Safety shutdown device Vacuum gas oil desulfurization unit, hydrogen manufacturing unit No.1, topping unit No. 2, vacuum distillation unit No. 2, hydrogenerated desulfurization unit No. 4
Effects on shipment Currently under investigation
Future plan The Fire Department and the Police will conduct an on-site investigation at 9:00 a.m. on April 17 (Monday).